All sites below Pugwash on the list have the same status as Pugwash with the exceptions of:
- Higgins Mountain (Feasibility study complete)
- 70MW Cumberland County (Interconnection request valid)
- 10MW Richmond County (Feasibility study in progress)
- 50MW Halifax - steam turbine (Interconnection request valid)
The six projects ahead of Pugwash are variously listed as "generator interconnection agreement tender" (#8 Guysborough), "Impact/optional study in progress"or "feasibility study complete".
6 comments:
Anybody hear the news on Hurricane Noel, is it headed this way?
Hi Lisa, I'm just wondering which in the list is Higgins, everything is by numbers that I can see. Thanks
My info says: Higgins Mountain ID# is 126
Thanks Lisa, do you have the info for the names of the other numbers? If so then can I send you an email to send this info to me, Thanks T
t, I have most of the Cumberland Co sites identified - albeit from a rather poor map!
You can e-mail if you like. There's a link here somewhere ....
Thanks Lisa, I've sent you an email. T