Saturday, July 9, 2011

Wind developer vows to ease military’s worries

Greenwood: Turbines would be too close


Military concerns about a $60-million Annapolis Valley wind project won’t shoot down the energy project, the developer says.

Sprott Power Corp. plans to build a 12-turbine wind farm in the Hampton Mountain area, four kilometres north of Bridgetown.

Officials at 14 Wing Greenwood say turbines shouldn’t be allowed within a 46-kilometre radius of the Canadian Forces base because turning blades could interfere with radar. The base is 40 kilometres from the proposed wind farm.

Jeff Jenner, Sprott Power president, said Friday the Toronto company is working to address military concerns and has hired a consultant to study the issue.

"I think we will be able to find a couple of solutions that will work for everybody," Jenner said.

But Sprott doesn’t plan to relocate any towers, which have received provincial environmental approvals, he said.

The military voiced its concerns to Sprott during the environmental approval process last year, the company president said. Base officials raised their objections again this week during public meetings into new wind turbine rules proposed by Annapolis County.

A spokesman for 14 Wing Greenwood was out of the province Friday and not available for comment. But Maj. Al Harvey told a public meeting in Kings County in January that having turbines within a 46-kilometre radius of the base could make it difficult for air traffic controllers to see aircraft flying in and out of the Greenwood on their radar screens.

"It is becoming a worldwide major problem for all air traffic control radars dealing with significant interference from nearby wind turbines," the minutes of the meeting quote Harvey as saying.

Jenner said Friday base officials have told Sprott the turbines could interrupt radar coverage with an emergency runway.

"There’s some mitigating work that can be done because wind farms are situated around the world within 40 kilometres of radar installations," he said.

Jenner said it may be possible to adjust radar angle or have a plan in place to halt turbines in case of an emergency, depending on how often the runway is used.

The latest radar systems are able to recognize turbines, the company president said.

Sprott is still in the process of receiving renewals for building permits it held for properties in Arlington, Arlington West and Hampton, Jenner said.

In April, Sprott asked the Nova Scotia Supreme Court to overrule a municipal decision denying the renewal.

Annapolis County announced last month it was changing its planning strategy to allow Sprott to proceed with most of the turbines.


http://thechronicleherald.ca/Business/1252513.html

Thursday, July 7, 2011

Wind farms’ business could take off

N.S. will call for renewable power plans next year


Wind farm developers will get a chance early next year to apply to get their large-scale projects off the ground.

An Energy Department spokeswoman said Wednesday a call for bids from independent producers is expected in the first part of 2012 to develop the next round of large renewable energy electricity projects in the province

"The expectation is that it will be mostly wind," Nancy Watson said in an interview.

She said there’s nothing stopping applications for other types of green energy projects.

The department announced Monday that it has chosen an independent renewable electricity administrator to oversee the bid process and make recommendations to the department.

Power Advisory LLC, based in Carlisle, Mass., will help draft the call for bids and power purchase agreement. The consultant, which also has an office in Toronto, will also hold consultations in the fall on the bid process.

Watson said department officials had their first meeting with the consultant by teleconference on Tuesday.

Independent producers will be bidding for a share of the 300 gigawatt hours per year of electricity that the province wants to buy from them. That’s equal to 100 megawatts of wind power. Nova Scotia Power, the province’s privately owned electric utility, will develop an equal amount of renewable electricity under the province’s renewable energy plan.

The strategy calls for 25 per cent of Nova Scotia’s electricity to come from renewable sources by 2015 and 40 per cent by 2020.

Several wind farm developers have unveiled proposals for large projects, including ones in Jeddore, Weymouth, Parrsboro and Cape Breton, in anticipation of the call for bids.

Some developers have said they expected proposals to be sought this summer.

Dan Roscoe, chief operating officer of Scotian WindFields Inc., said he doesn’t think the industry will have any problems with the bid call being early next year.

"It’s something that we think is a good step," he said of having the administrator in place.

"Essentially what would happen before is that the procurement process was being overseen by Nova Scotia Power and they were also a generator. I wouldn’t go so far to say that they actually have a conflict of interest but it certainly creates the perception."

Roscoe’s company works on smaller, community-based wind projects, swhich will be able to supply 100 megawatts of electricity through the province’s new community feed-in tariff program.

The idea of having an administrator involved in large-scale projects was one of 25 recommendations made to the Dexter government last year in a report by Dalhousie University professors David Wheeler and Michelle Adams.

The Energy Department said Power Advisory’s work is expected to take nine months but the contract is for one year, with an option to renew.

The company will be paid an hourly rate of $255, plus legal fees.


http://thechronicleherald.ca/NovaScotia/1252086.html

Wednesday, June 29, 2011

New wind power bylaw drafted

ANNAPOLIS ROYAL — Annapolis County has drafted a new bylaw that will allow large-scale wind turbines on four areas of the North Mountain and an already designated location on South Mountain.

The proposed legislation follows a year of public meetings and an interim bylaw that restricted development until council had more time to study the issue.

The interim bylaw was never intended to stop wind farm development but it was designed to allow time for a bylaw to be developed that was right for the county, Warden Reg Ritchie said.

"It was important that residents had the opportunity to be included in any decisions made in this regard," he said in a news release. "The year spent researching wind farm development was essential in helping to explore the issues . . . and hone a draft bylaw that reflected what our residents said was important to them."

The new bylaw specifies four locations on the North Mountain, including the Delaps Cove-Victoria Beach and Hampton Hills area, along with an original designated area on the South Mountain.

"Locations for wind resource areas where large-scale wind turbines may be located were brought up repeatedly during the public meetings," said Ritchie. "The planning advisory committee listened to what was being said."

The committee also addressed other wind turbine issues including setback and separation distances from public roads, habitable buildings and property boundaries and the decommissioning of large wind turbines.

Public meetings on the proposed bylaw have been scheduled for the Bridgetown Lions Hall on July 5 and the Lower Granville Hall on July 7. Both begin at 7 p.m. It may also be viewed on the municipality’s website at www.annapoliscounty.ns.ca.

No date was given for when council expects to pass the bylaw.


http://thechronicleherald.ca/NovaScotia/1250959.html

Digby loosens rules for wind turbines


DIGBY — If you live in Digby County, a wind farm could be coming to a vacant field near you.

The Municipality of the District of Digby passed a motion Monday to amend its land-use bylaw dealing with wind turbine developments.

In doing so, it paved the way for a third tier of mid-sized wind turbine developments. Mini wind farms may now sprout in fields or on vacant lots that meet the new regulations.

"The proposed amendments will introduce a new class of turbine — community scale wind turbine(s)," said municipal warden Linda Gregory at Monday’s public hearing.

After several written and oral submissions had been made, mostly urging caution, council passed the proposed amendment to their land-use bylaw allowing for community scale windmill projects.

The amendment now goes to the Department of Municipal Affairs for ministerial approval, Gregory said.

As part of the province’s efforts to promote power production from renewable resources, a community-based, feed-in program was established, a handout from the municipality said.

Participation in such programs is restricted to municipalities, First Nations, co-ops, community and non-profit groups.

The new community scale turbines will be slightly smaller than commercial types. The electricity they generate will be used by Nova Scotia Power in the region, the municipal briefing document said.

The turbines may be set up in clusters on an approved piece of land where electricity could be generated and sent off-site.

The municipality already allows property owners to erect small, personal use domestic windmills for on-site power. The community-based turbines will fall somewhere in the middle of personal- and industrial-use turbines.

"There seems to be an absence of consideration of the good neighbour policy which considers the rights of citizens who already have a property adjacent to a proposed wind turbine installation," Shirley Langpohl of Gilberts Cove told councillors.

"We believe these citizens need to have their right to undisturbed enjoyment of their property protected," she said.

She suggested that the written permission of all nearby landowners be required before a project starts. The bylaw amendment also allows turbines to be erected without an environmental assessment and that’s wrong, she said.

The amendment stipulates a minimum setback of twice the height of a turbine from any property boundary and a maximum noise level of 45 decibels at any property line. More than one wind turbine would be allowed on one lot.

That’s an open invitation for the creation of wind farms within communities, said Sandy Cove resident Ashraf Mahtab. He said that section of the amendment should be removed.

It wasn’t.

Warden Gregory voted against the motion. She said council should have looked at a specific or maximum number of wind turbines per property.

The amendment allows a non-profit or other qualified group to partner with a commercial wind company if the non-profit venture owns 51 per cent or more of the entity.

No non-profit group had asked Digby municipal council to consider community-scale wind farm regulations. But Scotian WindFields Inc., the developer of Digby Neck’s commercial wind park (now owned and operated by Nova Scotia Power) made a request in February.

The company sought the change because the municipality’s land-use bylaw stipulated that the energy produced by smaller type turbines be consumed on-site. But the province’s new strategy envisions smaller turbines selling power to the grid, said Dan Roscoe, Scotian WindField’s chief operating officer, on Tuesday.

"These are smaller-scale wind turbines and shouldn’t be confused with the size of turbines that are at the Digby Neck wind farm . . . the utility grade."

He said 45 decibels is comparable to ambient noise outside on a windy day.

Scotian WindFields is affiliated with community organizations throughout the province, he said, such as Bay WindField Inc. in southwestern Nova Scotia.

A qualified group could sell its electricity to Nova Scotia Power. The provincial utility review board has created a special rate that provides a reasonable rate of return for investors in these projects, Roscoe said.


http://thechronicleherald.ca/NovaScotia/1250886.html

Thursday, June 23, 2011

Amherst wind farm taking shape


A $61-million wind farm slated to be up and running in Amherst early next year will have about 50 employees.

"People are actually already on the site working," Jeff Jenner, president and CEO of Sprott Power Corp. of Toronto, said in an interview Wednesday after Premier Darrell Dexter helped break ground for the wind farm.

Sprott, which owns wind farms in Cape Breton, and Firelight Infrastructure Partners, also of Toronto, are leading the project. Suzlon Wind Energy Corp., an energy multinational, is also involved and has hired DSTN Trenton to manufacture the steel towers for the wind turbines.

"I think the reason we’re willing to invest the $61 million here is because your government has a great energy platform and it will attract investors, such as Sprott and others," Jenner said.

"Nova Scotia is at least the only provincial jurisdiction where its commitment to a renewable portfolio standard has what I would call teeth, in that it’s law and people must abide by it, and as a result, people are helping companies like us make it happen."

The project will feature 15 wind turbines with a capacity of 31.5 megawatts, enough energy to power 10,000 homes.

The Dexter government says the wind farm will not only boost the economy in the Amherst area but will help the province reach its renewable electricity targets. The province has set a goal of getting 25 per cent of its electricity from renewable sources by 2015 and 40 per cent by 2020.

Amherst Mayor Robert Small couldn’t be reached for comment Wednesday.


http://thechronicleherald.ca/Business/1249836.html

Sunday, May 29, 2011

Firm inks deals for Cumberland wind farm


Halifax-based Shear Wind Inc. has secured enough privately owned land for a proposed wind farm near Parrsboro, Cumberland County.

The company recently signed lease agreements with 10 to 12 landowners in the area, said Mike Magnus, president and CEO of Shear Wind.

"It will end up being between 6,000 and 8,000 acres," Magnus said Friday.

The wind farm would be located behind Harrison Settlement on Canaan Mountain.

The company intends to sell energy to Nova Scotia Power but is also investigating the possibility of shipping power out of the province to other markets.

"We are hoping for the opportunity to participate in a domestic (request for proposals) and then also be able to investigate a similar-size wind farm, or larger, to export out of Nova Scotia."

The first phase of the wind farm would be for about 50 megawatts and would cost between $125 million and $130 million to build, Magnus said, and the project could expand to generate as much as 150 megawatts.

Shear Wind, which trades on the TSX Venture Exchange (SWX), recently completed the first phase of the Glen Dhu wind farm, a 62.1-megawatt facility located between Pictou and Antigonish counties.

"The topography (near Parrsboro) is very similar to our Glen Dhu site. It has got elevations of anywhere between 240 to 290 metres," Magnus said.

The company has applied to Nova Scotia Power for transmission access and plans to immediately put up a couple of wind measurement towers on the mountain.

"We think that there is wind up there. We will validate that over the next couple of months, and then from the wind towers, we will be able to determine what technology best works on that particular site."

Magnus said there is a lot about the Canaan Mountain site that is attractive.

"What you need is a significant amount of scale to make the economics work right. . . . What we like here is that we have a very strong transmission system to get us to the main spine line out of the province. Those are all important components of building any type of wind farm."

Some community opposition exists to the Glen Dhu wind farm because of noise levels and environmental factors.

Magnus said the Canaan Mountain site is far removed from any homes, and is also far enough away from blueberry farms that it won’t interfere with operations.

Some of the landowners involved in the lease agreements are blueberry farmers who have unused acreage, he said.


http://thechronicleherald.ca/Business/1245625.html

Monday, May 16, 2011

Wind farm proposed for Victoria County

Project would be biggest in province


A consortium of Nova Scotia and U.S. companies wants to build a $2- to $3.5-billion wind farm and transmission system in the Cape Breton Highlands.

Highland Power Co. Inc. of Sydney is proposing a 100- to 300- megawatt wind project in Victoria County with a transmission line to other parts of Nova Scotia and New England.

"It’s a very large project. We’d be looking at several years of development," Jeff MacKinnon, a director of Highland Power, said Thursday.

The venture could be twice as large as any existing wind farm in the province. The biggest is Shear Wind Inc.’s Glen Dhu project in Antigonish County. Completed in March, it has 27 turbines generating 62 megawatts of electricity, enough energy to power 18,000 homes.

The Highland Power wind farm would be built on Highland Road, a forested area that is not residential and has been clear cut, MacKinnon said.

The consortium includes U.S. companies Starwood Energy Capital and Charles River Associates, Northern Innovations, a Nova Scotia holding company; the Eskasoni First Nation, RMSenergy Ltd., which owns the Dalhousie Mountain wind project; and Daewoo Shipbuilding and Marine Engineering, which is opening a wind turbine plant in Trenton.

The consortium was incorporated in Nova Scotia on March 25. Its president is Peter Knollenberg, a West Palm Beach, Fla., businessman and shipwreck explorer. Sydney businessman Jim Kehoe is also a director, according to the provincial Registry of Joint Stock Companies.

Kehoe couldn’t be reached Thursday for comment.

MacKinnon, who says he was a fisherman and part of a treasure-hunting venture before getting into alternative energy, said the project is in the "very, very preliminary" stages. The earliest construction could start would be 2013 or 2014, he said.

"All I’m doing right now is laying out the groundwork to gauge the level of interest in a project like this," he said in an interview from Sydney.

MacKinnon said consortium officials have met with the provincial Energy Department and Nova Scotia Power to talk about their plans.

He said the group will be making a proposal to the province when the government issues a call this spring for expressions of interest in developing a 130-megawatt wind farm.

In a letter last week to Victoria County council, Highland Power says the project’s first phase would generate 100 to 200 megawatts of electricity.

Bruce Morrison, warden of Victory County, said the municipality is interested in the project, which could create lots of jobs in the area.

"I’m certainly open in having those discussions and I know council is as well."

Morrison said the wind farm site is almost 20 kilometres from Baddeck on a road that runs from the top of Hunters Mountain to Wreck Cove, where Nova Scotia Power has a generating station.

The warden said the municipality would have to develop a bylaw to allow the project. That process would involve public consultation, he said.


http://thechronicleherald.ca/Business/1243156.html