Tuesday, January 12, 2010

Wind farm up in the air

Amherst-area project missed deadline

More uncertainty is hanging over one of Nova Scotia’s proposed multimillion-dollar wind energy projects.

Acciona Energy Canada is reviewing the feasibility of its proposed 30-megawatt wind project near Amherst that would provide enough electricity for 10,000 homes.

The project, to include 20 turbines, has been on hold since last March and missed the Nov. 30 deadline in its contract to begin providing electricity to Nova Scotia Power.

"We’re continuing to look for a good solution for it," Acciona spokesman Eric Schneider said Monday in a telephone interview from the Spanish conglomerate’s North America headquarters in Chicago.

"I wouldn’t say it’s never going to be feasible, but in the current climate it’s definitely made it so that we have to look at options to improve the financial viability of the project."

The $55-million wind project was halted because of the downturn in the economy and an increase in costs, he said.

Many variables, including financing costs, have increased considerably since Acciona, one of the world’s largest renewable energy companies, signed its agreement with Nova Scotia Power in 2008.

"Just like many other projects throughout Canada that ran into that scenario," Acciona spokeswoman Micaela Whalen said Monday.

"Because right now, we’re sitting down and looking at our assets and determining what will work and what will make the project financeable and a project that makes sense for both our company and Nova Scotia. That’s what is being determined right now."

Mr. Schneider was uncertain whether Acciona has forfeited its deposit to Nova Scotia Power because of missing the Nov. 30 deadline to begin generating electricity.

According to other wind power developers who signed contracts with Nova Scotia Power, the deposit was $25,000 per megawatt. That would make the deposit for Acciona’s 30-megawatt project $750,000.

"I’m not sure," Mr. Schneider said. "I’ll check into that."

Last week, The Chronicle Herald reported that Shear Wind Inc. of Bedford had to forfeit a $500,000 deposit to Nova Scotia Power for missing the Nov. 30 deadline. Renewable Energy Services of Lower Sackville also missed the deadline, and its deposit was $550,000.

Renewable Energy spokesman Jim Meredith told The Chronicle Herald last week that it’s not fair for Nova Scotia Power to take the money, considering the provincial government gave the utility a time extension on its agreement to buy electricity generated from renewable sources. Nova Scotia Power did not pass on that extension to its suppliers, Mr. Meredith said.

Last fall, the province added a year to Nova Scotia Power’s deadline for obtaining five per cent of its electricity from renewable sources. The new deadline is Dec. 31, 2011.

Nova Scotia Power signed six contracts with independent power producers in 2008 for 247 megawatts of electricity, enough power for 87,000 homes, to be generated by late 2009. Only RMS Energy, which has installed 34 wind turbines west of New Glasgow, is producing electricity.

Nova Scotia Power spokesman David Rodenhiser said the utility will need 200 megawatts of green electricity by 2011 to meet the government’s target.


http://thechronicleherald.ca/Business/1161760.html

Monday, January 11, 2010

Turbines up, not all running

Testing will determine amount of power that can be generated in given winds

The wind turbines atop Dalhousie Mountain began sending electricity to the power grid late last month, but not all the vanes will spin all the time throughout January.

Although they’ve been operating since Dec. 23, each of the 34 identical machines must undergo a turbine reliability test to demonstrate it can produce a given amount of power in a given wind, RMSenergy president Reuben Burge said Sunday.

The tests need certain wind speeds, so January’s variable weather has created challenges in trying to complete the process. But Mr. Burge expects the tests will be completed by the end of the month. The tests mean that some turbines will be shut down at various times.

"On and off, you’ll see them," Mr. Burge said during a cellphone interview as he headed toward the Pictou County site to continue the tests.

A breeze of 20 to 25 kilometres an hour is enough to produce electricity, but more wind doesn’t produce more electricity, he said.

"Once it gets to a certain point, it doesn’t matter how strong it is," he said, adding that the vanes are designed to let high winds slip past. If the wind is too high, the turbines operate roughly.

The RMSenergy wind farm, Nova Scotia’s largest, can produce a total of 51 megawatts of power when all the 1.5- megawatt turbines are running.

That’s enough electricity for 17,000 homes.

The electricity is sold to Nova Scotia Power through a long-term fixed-price purchase agreement, a method designed to stabilize energy costs.

The project has generated intense community interest, Mr. Burge said.

It created more than 100 summer and fall construction jobs and 10 full-time jobs to operate the wind farm. Local workers have filled most of the jobs.

Mr. Burge said he plans to operate the site for the next couple of years while assessing opportunities.

"If the market and the economics make sense and the wind blows as it’s supposed to, then I’d plan for another phase," he said.

http://thechronicleherald.ca/NovaScotia/1161618.html

Saturday, January 9, 2010

Wind firm, NSP to split hookup bill

Nova Scotia Power and a wind developer in Amherst must split the $4.35-million bill to connect a proposed wind project to the power grid, the Nova Scotia Utility and Review Board ruled Friday.

The utility must hand over $2.18 million and Spanish conglomerate Acciona Energy will pay $2.35 million towards the connection costs of the 30-megawatt wind park in Cumberland County.

The board said this was a "reasonable approach" to resolve the dispute between NSP and Acciona’s representative Amherst Wind Power LP.

Acciona signed a power purchase agreement with the power company in May 2008. The wind project was supposed to be operating by Nov. 30, 2009, but it not in operation and its future is uncertain.

Acciona, which has headquarters in Chicago, did not return phone calls Friday.

http://thechronicleherald.ca/Business/1161283.html

~~~~~~~~~~

UARB decision can be found at: http://www.nsuarb.ca/images/stories/pdf/Decisions/10Jan/168931%20nspi%20and%20amherst%20wind%20power%20lp.pdf

A powerful loophole

NDP admits NSP’s extended deadline had no conditions

The Dexter government failed to ensure wind power developers would get a break from Nova Scotia Power when it extended the power company’s renewable energy deadline, Energy Minister Bill Estabrooks admitted Thursday.

"It’s something we certainly probably should have included," Mr. Estabrooks said after the weekly cabinet meeting.

The minister was commenting on this week’s Chronicle Herald story that Bedford company Shear Wind Inc. had to forfeit a $500,000 security deposit to Nova Scotia Power Inc. for missing a Nov. 30 deadline for providing the utility with green electricity.

Renewable Energy Services of Lower Sackville also missed its Nov. 30 deadline, and its deposit was $550,000.

Company spokesman Jim Meredith told The Chronicle Herald this week that it’s not fair of Nova Scotia Power to take the money, considering the province gave the utility an extension on its agreement to buy electricity generated from renewable sources. Nova Scotia Power did not pass on that extension to its suppliers, Mr. Meredith said.

This fall, the province added a year to Nova Scotia Power’s deadline for obtaining five per cent of its electricity from renewable sources. The new deadline is Dec. 31, 2011.

Mr. Estabrooks said the province could have made a similar break for wind energy producers a condition of Nova Scotia Power’s extension.

"In light of the fact that there was . . . some slack which was delivered to NSP, I mean in return we would hope that there would be that sort of shared relationship with some of these other private contractors," the minister said.

He said he would raise the issue with Nova Scotia Power CEO Rob Bennett when they next met.

Mr. Estabrooks ended up speaking with Mr. Bennett late Thursday afternoon, a company spokesman said.

Mr. Bennett "explained the complex nature of these contracts and how each of the contracts is unique in its own right, and how we’re dealing with each of the producers in an equitable fashion," David Rodenhiser told The Chronicle Herald.

He said "our approach to working with the producers hasn’t changed."

Meanwhile, Premier Darrell Dexter said he’s not sure Nova Scotia Power’s decisions were exactly as reported, and there’s more to come on the situation. He wouldn’t elaborate.

The premier said he knows of one independent power producer who absorbed extra costs to make sure the deadline was met.

Nova Scotia Power signed six contracts with independent power producers in 2008 for 247 megawatts of electricity, enough power for 87,000 homes, to be generated by late 2009. Only RMS Energy, which has installed 34 wind turbines west of New Glasgow, is producing electricity.

With Michael Lightstone, staff reporter


http://thechronicleherald.ca/Business/1161178.html

Thursday, January 7, 2010

$500,000 penalty 'not fair'

Wind firm misses NSP deadline, argues province gave utility its own extension

A Nova Scotia wind developer doesn’t want to hand over $550,000 to Nova Scotia Power for not meeting its deadline to deliver green electricity.

"It’s a big issue," said Jim Meredith of Renewable Energy Services Ltd. "That’s a lot of money."

The private wind company, headquartered in Lower Sackville, signed a power purchase contract with NSP in February 2008 to provide the utility with 22 megawatts of wind-generated electricity by Nov. 30, 2009.

Under the contract, the company provided a security deposit for $550,000, or $25,000 per megawatt, to NSP in case the company didn’t meet the terms of the contract, he said.

"Contractually, we signed a contract saying that we’re supposed to be in operation by Nov. 30, 2009. We put a security deposit down based on that. From a pure contract, I would say we’re offside. From a fairness point of view, I would say it is not fair," said Mr. Meredith.

Mr. Meredith said the firm was hit hard by the financial crisis in 2008, which made borrowing money difficult for its proposed $55-million wind project at Statia Terminals in Cape Breton.

The company lobbied both the provincial government and NSP for an extension, he said.

He said the provincial government gave the power utility an extension in November to buy renewable energy from independent power producers because the financial meltdown has stalled many of the projects.

"The theory is NSP would pass it along to the people that bid," he said. "But they haven’t."

Mr. Meredith said the company plans on continuing to talk to the utility and hopes to have an answer in a month.

"I can’t say we have or haven’t forfeited (the money) because . . . it’s a decision that hasn’t been made by either party," he said.

The Chronicle Herald revealed on Wednesday that Shear Wind Inc., a Bedford renewable energy company, had to pay NSP $500,000 for not producing the promised green electricity on time from its proposed $160-million wind park near New Glasgow.

The company was unable to get the necessary financing.

Renewable Energy Services Ltd. and Shear Wind are two of the six groups that signed contracts in 2008 with NSP to sell wind-generated electricity, for delivery in late 2009.

NSP contracted for 247 megawatts of power, enough for 87,000 homes. The utility signed up with the independent power producers to meet the government’s target of 25 per cent of its electricity from green sources by 2015.

Of the six contracts, only RMS Energy, which has 34 wind turbines in the Cobequid Range, 25 kilometres west of New Glasgow, is producing electricity on schedule, according to NSP’s website.

NSP spokesman David Rodenhiser would not say which companies have forfeited their security deposit.

"Nova Scotia Power wants to see all of these projects move forward. We have worked closely with the developers of these projects, allowing flexibility where possible, to help move the projects forward and bring more renewable energy to the grid as soon as possible for the benefit of our customers," Mr. Rodenhiser wrote Wednesday.

There are 75 wind turbines across the province generating electricity for the utility, according to its website.

The other wind developments that signed long-term purchase power agreements with NSP have been delayed, purchased by other developers or remain uncertain.

Last April, NSP purchased developmental rights to a 22-turbine proposal for Nuttby Mountain from bankrupt EarthFirst Canada Inc. of Calgary. The $120-million wind farm, about 20 kilometres north of Truro, is expected to be operational this year.


http://thechronicleherald.ca/Business/1160946.html

Wednesday, January 6, 2010

Delay costs Shear Wind

Energy firm forfeits $500,000; wind farm behind schedule


Shear Wind Inc., a renewable energy company, must pay $500,000 to Nova Scotia Power for not producing green electricity on time.

"It’s a contractual obligation. Obviously, we really would have liked some relief from it," Bill Bartlett, Shear Wind’s chief financial officer, said in an interview Tuesday.

The Bedford company reported the writedown in its year-end financial statements filed with securities regulators before Christmas.

Under the contract signed in April 2008, Shear Wind promised to deliver 20 megawatts of wind-generated energy to NSP by the end of November 2009.

Shear Wind, a publicly traded company formed in 2004, provided a $500,000 performance security deposit held by NSP in case the company didn’t deliver.

The company had to forfeit the cash Nov. 30, it reported in documents.

This is tough news for a company that has incurred significant losses over the last three years, including a $628,182 loss last year, according to company documents.

"Obviously, we don’t have a lot of comfort giving someone $500,000, but a contract is a contract," said Mr. Bartlett.

NSP spokesman David Rodenhiser would not comment about the Shear Wind contract or any other wind contracts for confidentiality reasons.

Shear Wind was delayed in starting its proposed $150-million wind turbine park near New Glasgow, called Glen Dhu, because of the collapse in the world credit markets in the 2008.

The company, like many others, was unable to borrow the money to finance the project.

Mr. Bartlett said the utility was sticking to the contract and Shear Wind was unsuccessful in trying to negotiate not paying the penalty.

Last month, Shear Wind had an infusion of cash with a Spanish billionaire investing $27 million in the company and giving the Nova Scotia project a kick start.

The company expects the project to start producing electricity later this year.

Mr. Bartlett said financial statements for the period ending Aug. 31 included the $500,000 loss since the company knew it was not going to meet its fall commitment.

Shear Wind was one of six companies that signed contracts in 2008 with NSP to sell wind-generated electricity for delivery in late 2009.

NSP contracted for 247 megawatts of power, enough electricity for 87,000 homes.

The wind developments have been critical to moving Nova Scotia beyond its heavy reliance on dirty coal-fired electrical generation. The wind contracts are key for the utility to meet the government’s renewable energy targets of producing 25 per cent of electricity from green sources such as wind by 2015.

Of the six contracts, only RMS Energy, which has installed 34 wind turbines in the Cobequid Range 25 kilometres west of New Glasgow, is producing electricity to the power grid on schedule, according to NSP’s website.

Mr. Rodenhiser said RMS Energy has been producing electricity for over a month for the utility.

Currently, NSP has 75 wind turbines generating electricity for the privately owned utility across the province, he said.

The other wind developments that signed long-term purchase power agreements with NSP have either been delayed, purchased by other developers or remain uncertain.

In April 2009, NSP purchased the developmental rights of the proposed Nuttby Mountain 22-turbine wind farm from bankrupt EarthFirst Canada Inc. of Calgary. The $120-million wind farm, located about 20 kilometres north of Truro, is expected to be in operation later this year.

Last month, NSP parent company Emera Inc. took a stake in another financially troubled wind farm in Digby. Emera made an undisclosed offer to purchase a 50 per cent interest in the project held by troubled SkyPower Inc. of Toronto, which had partnered with Scotian WindFields.

Renewable Energy Services Ltd. proposed to build an 11-wind turbine farm at Statia Terminals in Point Tupper with a capacity of 24 megawatts, enough to produce electricity for 6,000 homes.

Company officials were unavailable for comment. NSP does not have the project listed on its website as operational.

Acciona Energy of Spain, with offices in Chicago, proposed to build a 20-turbine wind farm on the marsh outside Amherst.

NSP reported earlier this year to government regulators that it had been delayed.


http://thechronicleherald.ca/Business/1160834.html

Tuesday, December 1, 2009

Nuttby wind farm approved

$120-million, 22-turbine project to be financed by NSP customers’ power bills

Nova Scotia Power has been given the green light to develop a $120-million wind farm in Colchester County.

The provincial Utility and Review Board approved the 22-turbine project on Nuttby Mountain in a decision released Monday.

"The board . . . is satisfied that the project is in the best interest of the ratepayers and should proceed," the board wrote in a 23-page decision.

Nova Scotia Power customers will pay for the project through power bills.

However, government regulators rejected the company’s request to be able to sell 51 per cent interest in the wind farm.

Nova Scotia Power had hoped to get advance approval for the sale, which would allow the wind-generated electricity to be counted toward the 2011 independent green energy target. (The utility has to buy five per cent of its electricity from independent energy sources by that date.)

The review board argued that it is up to the courts to decide on the interpretation of provincial legislation, and a ruling now would be "simply premature."

Nova Scotia Power originally selected the 45-megawatt wind project as part of its request for proposals in 2007 for renewable energy from independent power producers.

Financial troubles drove the developer — EarthFirst Canada Inc. of Calgary — into bankruptcy and Nova Scotia Power picked up the development rights in April.

The utility filed an application with the board in September, asking for a decision by today to get the project back on schedule and allow the wind farm to qualify for federal government incentives.

To qualify, the project must be under construction this year and be completed by March 31, 2011.

Nova Scotia Power filed a letter on Nov. 20 saying the federal government has agreed that the Nuttby Mountain project qualifies for $14 million in incentives.

The power company filed evidence that it could produce electricity cheaper than the wind farm’s original proponent could, and power customers would save $7.3 million over the 23-year lifespan of the project.

The wind farm project will include buying and erecting the turbines about 20 kilometres north of Truro and building a new substation and transmission lines.

Also on Monday, Nova Scotia Power’s parent company, Emera Inc. of Halifax, officially took a stake in another troubled wind farm in Digby.

Emera made an undisclosed offer to buy a 50 per cent interest in the project held by SkyPower Corp., a partner to Scotian WindFields. SkyPower Corp. entered into creditor protection when owner Lehman Brothers went bankrupt.

The deal was finalized Monday in the Ontario Superior Court of Justice and shows that a numbered company owned by Emera put in the offer for the assets.

Dan Roscoe, Scotian WindFields’ chief operating officer, said the project can now move forward.

"It’s certainly nice to have this stabilized and we are anxious to get going on the work," he said.

Emera spokeswoman Sasha Irving has stated it was easier for Emera to make the purchase than Nova Scotia Power, which would have had to seek regulatory approval.

Construction is expected to begin in January with electricity generated by next November. The 30-megawatt wind project has a power-purchase provision with Nova Scotia Power, signed in May 2008.

Thirty megawatts of electricity can power 10,000 homes.

The Digby wind park is key for the utility to meet government’s renewable energy target of producing 25 per cent of its electricity from green sources by 2015.


http://thechronicleherald.ca/Front/1155507.html