Shear Wind project faces delay

Company to erect 12 turbines this year, remaining 15 by next March


A shortage of wind turbines has meant one of Nova Scotia’s proposed wind farms will be delayed, but the company running the operation will deliver the amount of electricity it promised to Nova Scotia Power, The Chronicle Herald has learned.

Shear Wind Inc. will erect only 12 of 27 turbines by Dec. 31, and the remainder will be installed by March 31, 2011, company president Mike Magnus said Tuesday night after a presentation at Saint Mary’s University in Halifax.

Despite the setback, the Bedford renewable energy firm will still meet its contractual obligations to provide Nova Scotia Power with 20 megawatts of wind-generated electricity, enough for almost 6,000 homes, by the end of December under a contract signed in 2008.

"We are anticipating putting up 12 turbines by the end of the year and the balance of turbines before March 31," Magnus said.

"That’s our plans."

The company probably spent "too much time assessing" which turbines would be best for the project and consequently ordered too late, he said.

In May, Shear Wind signed a contract with German wind turbine manufacturer Enercon for an estimated $100 million.

Shear Wind is developing the $150-million Glen Dhu wind power project to produce 60 megawatts of power. It straddles Antigonish and Pictou counties, and was scheduled to have 27 turbines up and running by the end of December.

This is another setback for the project, but Shear Wind was unable to secure financing until late last year when a Spanish utility conglomerate bought a 62 per cent stake in Shear Wind for $27 million.

Shear Wind had to forfeit a $500,000 performance deposit to Nova Scotia Power after it failed to deliver electricity to the utility by the end of last year.

Shear Wind’s project is one of six contracts Nova Scotia Power signed in 2008 with wind developers for 247 megawatts of electricity, enough for 87,000 homes, to be generated by late 2009. Only RMS Energy, which has installed 34 wind turbines west of New Glasgow, is producing electricity.

Nova Scotia Power has purchased two of the struggling projects, which should be fully operational later this year, and bought a 49 per cent stake in Renewable Energy Services Ltd.’s Point Tupper wind project, which is already producing power, said Patty Faith, Nova Scotia Power spokeswoman, on Wednesday.

A 30-megawatt wind project proposed by Acciona Energy Canada for Amherst has been halted for many reasons, including financing costs and the downturn in the economy, said Micaela Whalen, Acciona spokeswoman, from Chicago on Wednesday.

"The devaluation of the Canadian dollar, combined with rising costs, made the project more expensive to build and increasingly difficult to procure financing, and all those things are critical. We’re currently looking for a solution to make the project viable," she said.

Despite the Acciona project stalling and Shear Wind’s delay in installing turbines, Nova Scotia Power will meet renewable energy targets because the utility oversubscribed the amount of electricity required, said Faith.

"When all the projects that are currently under construction are completed, wind power will account for 280 megawatts of electricity in the province, which is about double what it was."

These wind projects will represent about 13 to 16 per cent of the province’s electricity supply.


http://www.thechronicleherald.ca/Business/1204593.html

Wednesday, September 29, 2010

N.S. limits access to energy documents


The Dexter government is only releasing a small number of the 57 documents it received about the province’s plan to increase the amount of green energy generated here.

On Tuesday, the province released five of the submissions containing advice about the province’s draft renewable electricity regulations but only after The Chronicle Herald filed a request under the Freedom of Information and Protection of Privacy Act.

The government sought public input on its new renewable energy strategy in May, and the public had until July 23 to submit ideas.

After being denied access to the submissions, The Chronicle Herald filed its request Aug. 25.

The material released to the newspaper offers advice on plans to increase the province’s renewable electricity supply. The province wants 25 per cent of its electricity to come from green sources by 2015.

In September, the Energy Department offered to expedite the process by asking The Chronicle Herald to select some of the 57 submissions for perusal. Then, the province said, it would ask those parties if they wished to have their submissions made public.

The newspaper requested seven documents but was given five, including submissions from Nova Scotia Power, Halifax law firm McInnes Cooper, papermaker NewPage, the Canadian Wind Energy Association and wind turbine manufacturer Enercon.

Two companies, Northern Pulp and Paper and Halifax-based renewable energy firm Shear Wind Inc., requested that their submissions remain private.

The government says it will eventually release all submissions after each individual, company or group has been contacted to determine whether entire sections may be made public or if there would be a partial release of documents.

"The process involved submissions by people who had, in some cases, confidential arrangements or commercial arrangements," said Bruce Cameron, the Energy Department’s director of policy, planning and services, on Tuesday.

The regulations are to establish eligibility for community-based projects and a process for determining how they get compensated, along with a special process to support the next stage of tidal development in the Bay of Fundy.

They also establish a new renewable electricity administrator to manage bids for larger projects from independent power producers.

Cameron said the regulations are being finalized and will soon be presented to cabinet for approval.

"Regulations will then be finalized by cabinet and then become law."

He said most of the submissions indicate "overwhelming support for the thrust and direction of the renewable electricity plan and a great deal of support for the main features of the community feed-in tariffs."

The tariffs guarantee producers of renewable energy a long-term contract in which they are usually paid a price higher than the market price for power they feed into the grid.

The wind energy association’s submission supports the government’s plan and estimates that six megawatts of new wind power by 2015 will lead to $19.5 million in annual local economic revenue and over 122 direct jobs. It also recommended a broad definition of "community," as it pertains to the tariffs, that includes every resident of Nova Scotia.

Nova Scotia Power, in its submissions, is urging government to provide a "clear definition" of the word community.

Nova Scotia Premier Darrell Dexter proclaimed this week Right to Know Week to raise awareness of the right to access information.


http://www.thechronicleherald.ca/Business/1204337.html

Tuesday, September 28, 2010

Biomass plan too risky, hearing told

NSP customers will be on hook if plant fails, consumer advocate says

If anything goes wrong with a plan to generate electricity by burning wood waste at a plant in Point Tupper, it will become the financial burden of Nova Scotia Power customers, the province’s consumer advocate has told the Utility and Review Board.

"The board should make a finding that exposing ratepayers to the risk of such additional costs is imprudent," John Merrick wrote in a rebuttal argument filed Friday with the board.

"Such a finding is amply supported on the evidence. As a result, the application should be denied."

Both sides are turning up the heat over a controversial proposal for a $208-million biomass power plant. Nova Scotia Power and its project partner, NewPage Port Hawkesbury, are behind the proposal.

The review board must approve the project if it is to proceed. The proposal faces opposition from energy consultants, environmentalists, businesses and Merrick, the consumer advocate.

A decision is expected within 90 days of submission of the final evidence. The board rejected a similar proposal last summer.

Merrick has raised concerns about the financial troubles plaguing NewPage Corp., the Ohio company that owns NewPage Port Hawkesbury, and the risk that Nova Scotia Power customers will be exposed to if the biomass project incurs additional costs or if NewPage Corp. fails.

Merrick was critical of NewPage Port Hawkesbury for saying that its parent company’s financial situation is no different from that of other companies in the forest products business.

"Doing business with NewPage has a higher risk than doing business with other forest products companies generally," Merrick stated.

During a public hearing earlier this month, a U.S. consultant working for the review board showed that NewPage Corp., which is owned by private investment firm Cerberus Capital Management LP, has $7 million in cash and $113 million available on a line of credit, but it also has a debt of $3.4 billion.

Liberty Consultants recommended that Nova Scotia Power go back and negotiate with two other companies offering biomass proposals, Northern Pulp Nova Scotia Corp. and Cape Breton Explorations Ltd.

Nova Scotia Power said Merrick’s previous comments about a possible restructuring of NewPage Port Hawkesbury’s parent company were "speculative."

"In fact, the experience in Nova Scotia suggests that the local mill operation, and the biomass plant that supports it, would continue as usual during the financial restructuring of a parent company," Nova Scotia Power wrote in its rebuttal arguments to the board.

The utility states that the "concerns" of other interveners "do not identify issues that should cause the board to reject the project; instead, the board should accept the evidence of those in support of the project, including NewPage and the Nova Scotia government."

Nova Scotia Power wants the review board to approve the biomass project to help it meet the province’s targets for producing electricity from renewable sources. The company would like to get the plant up and running by 2012.


http://www.thechronicleherald.ca/Business/1204103.html

Thursday, September 23, 2010

Biomass gets a push

NSP, NewPage urge immediate approval of Cape Breton energy project

Two of Nova Scotia’s corporate heavyweights defended their proposed $208-million wood biomass energy project before the provincial regulator Tuesday.

Nova Scotia Power and its largest customer, NewPage Port Hawkesbury, argue the controversial biomass project is in the "best interest" of electricity customers in Nova Scotia and should be approved without further delay.

For the project to go ahead, it must receive approval from the Nova Scotia Utility and Review Board, which is in the final stages of reviewing the proposed project. It would use wood to generate electricity.

In a last-ditch effort to win over the regulator, NewPage urged the board in its 53-page submission released Tuesday to approve the project without further conditions.

Meanwhile, its partner, Nova Scotia Power, warns any delays in approvals or having to negotiate with other companies for another biomass project could mean higher power bills for its 470,000 customers. The utility would like the power plant to be operating by 2012 to meet the province’s targets for producing electricity from renewable sources.

"Continued analysis and negotiation is not justifiable, nor would it be appropriate, given that the Port Hawkesbury biomass project is the best available economic option for customers," wrote Nova Scotia Power in 36 pages of final arguments to the board.

NewPage Corp., the Ohio company that owns NewPage Port Hawkesbury, a pulp and paper operation, has reported having only $7 million in cash and $113 million available on a line of credit. The company is $3.3 billion in debt and faces annual debt servicing charges of $330 million.

Despite increasing sales in its second quarter, NewPage reported a loss of $174 million.

Last week, consultants hired by the regulatory board voiced concern that the project poses "significant risks" to Nova Scotia Power customers.

The consultants, from Liberty Consulting in California, recommended to the board that Nova Scotia Power go back and negotiate with biomass proposals from Northern Pulp and Cape Breton Explorations Ltd.

NewPage lawyers refuted the consultants’ remarks about the company’s financial stability.

"Liberty’s expressed concern with the financial condition of NewPage Corp. was premised on a non-expert opinion based apparently on an Internet review of certain publicly available information," NewPage’s lawyers wrote.

The pulp and paper company also stated the future of any industrial enterprise is subject to the "vagaries of its market environment" and the proposed energy biomass project will "enhance" the Cape Breton mill’s future.

Nova Scotia’s consumer advocate John Merrick, along with a group of industrial customers, known as the Avon Group, and the Ecology Action Centre all recommended the board reject the proposed biomass project.

Merrick argues the project has its benefits but there are "excessive and unreasonable risks of increased costs for ratepayers and should not be approved."

"It would be of benefit to NewPage and provide improved operating conditions for one of Nova Scotia’s largest employers," Merrick wrote in his submission.

He also argues the financial circumstances facing NewPage’s parent company will ultimately affect the mill in Cape Breton.

"No matter how productive the Port Hawkesbury (mill) may be, it is not a stand-alone operation," he wrote. "The risk is sufficiently possible and the consequences sufficiently great that it makes the project unreasonable and imprudent for ratepayers."

The Ecology Action Centre in Halifax does not oppose energy production from forest biomass but is concerned over the supply of biomass and the long-term fuel costs for the project.

The public hearing into the NewPage and Nova Scotia Power proposal has concluded. Rebuttal arguments are due by Friday. Board spokesman Paul Allen has said the board’s policy is to try and issue all decisions within 90 days of receiving all evidence.


http://www.thechronicleherald.ca/Business/1203154.html

Wednesday, September 15, 2010

The 'beast' is launched

U.K. firm set to erect a giant turbine to harness tides of the North Sea. Could the Bay of Fundy be next?

A U.K. COMPANY that is about to commission one of the world’s biggest marine energy turbines off the coast of Scotland has targeted the Bay of Fundy for future projects.

"The Fundy tides are one of the best tidal resources in the world. The area will become a key market and we want to be a part of it," said Timothy Cornelius, chief executive officer of Atlantic Resources Corporation, in an interview Wednesday.

Cornelius said Atlantis Resources has reviewed the tidal energy potential of the Bay of Fundy and has reached the point where discussions with potential partners are in order.

"One of the things we’ve learned over the years (is) the need for strong, local partners is paramount for projects of this magnitude," said the CEO.

"We want to talk to potential partners for everything from fabrication, all the way up to installation," he said.



The latest, and possibly largest, marine power turbine debuted Wednesday on its way to the coast of Scotland’s Orkney Islands. Weighing 132 tonnes and measuring 22.5 metres tall, the AK1000 is built to withstand the harsh open waters of the North Sea. (Mike Brookes Roper)



Now that Atlantis has successfully installed one of its massive AK1000 turbines off the coast of Scotland’s Orkney Islands, the marine energy company is ramping up some European and Asian demonstration projects and remains keen about the Bay of Fundy.

"We’ll soon be connecting the AK1000 to the Orkney regional power grid. It will generate enough power for about 1,000 homes," said the CEO.

"This represents a major step forward in the commercialization of tidal power. I would say tidal power today is about where wind power was about 20 years ago," he said.

Cornelius said his company has to date conducted only some initial analysis of the Bay of Fundy, but is fully aware of the bay’s "enormous potential" as a natural energy generator.

He said the AK1000 it just the sort of "beast" that could withstand the brutal tides and troublesome siltation of the bay. It weighs in at about 132 tonnes, stands about 22.5 metres high and has two 18-metre-diameter rotors to take advantage of the ebb and flow of ocean tides.

The turbine was designed to be big and slow and dependable and was built to withstand the worst the North Sea can toss at it, said the CEO.

"The slow-turning blades are an extremely minimal threat to marine life and the turbine can function in depths of 30 metres."

He said his company is definitely interested in talking to potential partners in a demonstration project in response to the province’s recent call for proposals for more tidal demonstration projects in the bay.

Fundy Tidal Inc. of Westport is expected to place a test turbine on the seabed near Digby sometime this fall and hopes to begin commercial operation in three years.

Nova Scotia Power and partner OpenHydro placed an underwater test turbine in the Minas Passage in the Bay of Fundy last fall. The future of that project has been foggy after powerful currents broke two blades on the turbine.

European tidal firms eye Fundy

Source: Norwegian, German companies have expressed interest

The prospect of harnessing the Bay of Fundy tides to generate electricity has caught the attention of two European developers of tidal power, The Chronicle Herald has learned.

Hammerfest Strom of Norway and Voith Hydro of Germany are among five companies that have expressed interest to the provincial government, a source told this newspaper.

Hammerfest Strom is already in a joint venture with ScottishPower Renewables to install a one-megawatt pre-commercial turbine at the European Marine Energy Centre in the Orkney Islands. The turbine is expected to be fully operational next year.

Voith Hydro Ocean Current Technologies is installing a one-megawatt turbine off the Scottish coast, project developers reported. The turbine is to commence a two-year trial at the European Marine Energy Centre next year.

The European companies’ interest in the Bay of Fundy tides, the highest in the world, is exciting news, an industry watcher says.

"It would mean the Bay of Fundy is really attracting the attention of the leaders in large-scale tidal," said Chris Campbell, executive director of the Ocean Renewable Energy Group of Nanaimo, B.C.

"That’s the opportunity that Nova Scotia is right on the cusp . . . this being a science experiment and turning it into a business," he said.

Hammerfest Strom executives are coming to Nova Scotia next month and will meet with officials from the government and the Fundy Ocean Research Centre for Energy to look at the medium- to long-term possibilities in Nova Scotia, Campbell said.

"The real issue now (is) what are the real opportunities going to be beyond putting a single machine in the Minas Passage (Bay of Fundy)?" he said. "The industry needs to see they’ve got a place that they can start to get experience with arrays of these machines. Pilot power plants as opposed to machine demonstrations. That’s what everyone is looking at at this point."

Campbell will be in Halifax on Oct. 12 to attend a government meeting on drafting a commercialization strategy for tidal power in Nova Scotia.

Energy Department spokeswoman Tracy Barron would only confirm that the government received notice from five companies that they are interested. She would not identify the companies.

She said the department will soon issue a formal call for more detailed proposals.

Last week, the Atlantic Resources Corp. of the U.K. said it is interested in the tidal energy potential of the Bay of Fundy and is waiting for the government to issue its request for proposals.

A $10-million turbine that Nova Scotia Power and partner OpenHydro of Ireland lowered into the Minas Passage, about 10 kilometres west of Parrsboro, last November was damaged and will be hauled out of the water next month.

Nova Scotia Power discovered that two blades, made from blends of plastics and glass, on the 400-tonne experimental turbine broke off in May. The malfunction is forcing the company to pull the device out of the water a year ahead of schedule.

Two other companies, Minas Basin Pulp and Power of Hantsport and Clean Current of British Columbia, have also been chosen to test turbines in the Bay of Fundy but have delayed their projects until 2012.


http://www.thechronicleherald.ca/Business/1201853.html

Tidal firm sees 'opportunity'

German company confirms interest in Bay of Fundy project

German tidal power developer Voith Hydro is taking a look at the province’s latest proposal to test an underwater turbine to turn the tides of the Bay of Fundy into a source of energy.

"Yes, Nova Scotia is an opportunity," said Pierre Seguin, Voith Hydro’s head of business development, in Brossard, Que., on Tuesday.

He said the company heard the government’s request for proposal for a fourth berth in the Bay of Fundy has "hit the street."

"We will take a look at it, but it is an investment decision and it will have to go before our board," said Seguin.

The provincial government announced Tuesday it is looking for a fourth developer to try and harness the tides of the Bay for Fundy to generate electricity. The Energy Department received five responses to an expression of interest issued earlier this year.

Seguin confirmed Voith was one of those companies that showed interest to the government in a test project in the Bay of Fundy. The Chronicle Herald has reported that Norwegian tidal power developer Hammerfest Strom is also interested.

The proponent must demonstrate the financial capability to fund the expensive technology that can withstand the harsh conditions in the bay, along with a plan to monitor effects on the environment, according to the government.

The deadline for proposals is Oct. 20.

Last week, the Atlantic Resources Corp. of England said it is interested in the tidal energy potential of the Bay of Fundy and is waiting for the government to issue its request for proposals.

But on Tuesday a company spokesman in London said it was probably too soon for the company to submit a proposal.

The successful proponent will join three other developers — Nova Scotia Power, Alstom and Minas Basin Pulp and Power — that have berths on the ocean floor.

Nova Scotia Power and its technology partner, OpenHydro, of Dublin, Ireland, have experienced the trials and tribulations of developing working tidal turbines.

The two companies deployed a $10-million turbine in the Minas Passage about 10 kilometres west of Parrsboro last November. It was damaged and will be hauled out of the water next month.

Nova Scotia Power discovered that two blades made from blends of plastic and glass on the 400-tonne experimental turbine broke off in May. The malfunction is forcing the company to pull the device out of the water a year ahead of schedule.

Two other companies, Minas Basin Pulp and Power of Hantsport and Alstom of Switzerland, have also been chosen to test turbines in the Bay of Fundy, with their projects scheduled to be installed in 2012.

The government’s decision to find a company interested in testing another turbine was welcome news to the organization overseeing development of tidal power in the Bay of Fundy.

"It’s great because this is brand new technology and we welcome another party to test a new technology," said Matt Lumley, spokesman for the Fundy Ocean Research Centre for Energy. "It will be exciting to see how it unfolds."


http://www.thechronicleherald.ca/Business/1202030.html


Tuesday, September 14, 2010

NewPage difficulties complicating NSP biomass generation project



Considering the financial pressure on Ohio-based NewPage Corp., provincial electricity customers have a right to wonder why Nova Scotia Power Inc. would want to become involved in a deal with the paper company.

During provincial Utility and Review Board hearings last week, it was revealed that NewPage, which owns the NewPage Port Hawkesbury plant in Point Tupper, is carrying a heavy debt load requiring huge service payments.

A New York debt analyst who asked not to be identified told me Monday that Nova Scotia Power’s participation in the $208-million deal to build a biomass power-generating plant in conjunction with NewPage Port Hawkesbury is most likely an attempt to protect its largest energy customer.

NewPage is expected to make $80 million from the deal by selling waste wood to the power utility to be burned in the biomass boiler. That money will go a long way toward helping NewPage to service its debt.

Whether the provincial regulator will allow Nova Scotia Power to become involved in the NewPage biomass project, despite its desire to help its customer, is still up in the air.

NewPage, controlled by Cerberus Capital Management, L.P., which bills itself as one of the world’s leading private investment firms, lost US$174 million in the second quarter on sales of US$890 million and it was only holding US$7 million in cash and US$113 million in available credit.

The lack of cash on the books causes a big problem because NewPage has a debt of US$3.3 billion and is facing debt-servicing charges of US$330 million annually.

In its filing with United States regulators in August, NewPage indicated that management expects earnings in the third quarter before interest, taxes, depreciation and amortization will be US$90 million to US$100 million, compared with US$10 million for the second quarter of 2010 and US$140 million for the third quarter of 2009.

NewPage management said in its filing it expects to record a third-quarter loss of US$75 million to US$85 million, compared with a loss of US$174 million in the second quarter of 2010 and a loss of US$138 million for the third quarter of 2009.

Documents tabled during the board hearings in Halifax last week showed that a debt-research firm issued two reports showing heightened concern about NewPage.

CreditSights Inc. reported that NewPage was looking "toxic" and investors should avoid NewPage securities. It suggested that the bond market was "starting to price in the risk of potential default on the company’s cash coupons," due in the fourth quarter.

The risk of default may explain the importance of closing the biomass deal by the end of September.

Utility experts John Antonouk and Richard Mazzini of Liberty Consulting in California, hired by the board, suggested the biomass proposal should be rejected because, in their opinion, NewPage’s financial condition was already "troubling" and the biomass project has too many "significant risks" to Nova Scotia Power customers.

Simply rejecting the biomass project is more complicated than anyone would care to think about.

If NewPage Port Hawkesbury is dependent on this biomass project going ahead, a rejection of the proposal by the regular will have a huge impact not only on Nova Scotia Power, but also on northeastern Nova Scotia, which is highly dependent on the paper plant generating employment.

On the one hand, Nova Scotia Power’s desire to keep its largest customer in operation and paying its bills seems obvious. But, on the other hand, what if the biomass project gets the go-ahead and NewPage is forced to restructure anyway?


http://www.thechronicleherald.ca/Business/1201889.html

Monday, September 13, 2010

Firm weathers delay

It’s a year late, but Shear Wind expects to produce electricity by Dec. 31 at Glen Dhu


BAILEYS BROOK — Glen Dhu is Gaelic for dark valley, not a descriptive choice of name for the Shear Wind Inc. turbine project straddling the Pictou-Antigonish county line.

A thick, white fog often obscures the hustle atop the 250-metre-high ridge, where workers and machinery prepare bases for the project’s first turbine installation this fall.

It’s a year later than originally planned. That’s because it took about eight months for lenders to recover from the 2008 worldwide financial crisis, which meant the company couldn’t begin construction on time, Shear Wind chief operating officer Ian Tillard said Saturday.

That delay meant the company was unable to deliver electricity last December as scheduled, which resulted in a performance penalty against the company.

Investment in Shear Wind by the Spanish company Inveravante allowed construction to proceed at Glen Dhu (pronounced Doo), and it’s now on time, Tillard said.

At least 10 of the 27 turbines will begin transmitting electricity by Dec. 31. At that point, the remaining turbines will be in various stages of construction and will be hooked up to the grid by March 31.

Work began last winter with the cutting of trees and the building of 21 kilometres of roads through the wind-swept site, a long-time popular hiking and snowmobiling area that overlooks Lismore and the Northumberland Strait.

This coming week, workers will begin pouring concrete for the green-painted bases, also called cans or cones, which support the 80-metre towers. Construction is also underway on two electrical substations: a Shear Wind facility to collect the electricity from the turbines and a Nova Scotia Power unit to transmit it to the provincial grid, which runs through the site.

"That’s the main transmission line right through to Cape Breton and New Brunswick," site supervisor Grant Mason said Friday. "It was a big factor in determining where the wind farm would be."

"The substation is a vital part of this whole site."

After the concrete cures and electric modules are installed, the towers will be mounted over the bases. Beginning in mid-October, the silver-grey towers will be shipped by rail and road from Ontario and Quebec. The vanes will be trucked from the port at Sheet Harbour. The routes are determined ahead of time, following rigorous guidelines from the Department of Transportation and Infrastructure Renewal.

"There’s a lot of organizing to this," Mason said. "It’s all scheduled for when it’s needed. Once they start, they’ll all go up quickly."

The project will generate enough electricity to power 18,000 homes per year, he said.

About 40 to 80 people are employed by the project’s various contractors and sub-contractors, Mason said.

Shear Wind made a particular effort to employ local workers and to satisfy the landowners who leased the land and other community needs, he said.

There are no fences because Shear Wind leases, rather than owns, the property. However, constant security surveillance means that people can continue to visit the ridge and use its trails, Mason said.

The company is working with an Antigonish snowmobile club, a trail system, and regional tourism groups to maintain trails and, following construction, Shear Wind will install kiosks with interpretive panels describing wind generation.

The effort to include local citizens extended to naming the roads through the site. The main routes were named in honour of Don MacEachern, Harley Kellock and Gary Williams, three local men who supported the project but died before they could see it completed, Mason said. Names for the other roads were chosen by the landowners.

For safety reasons, the site also features two helicopter pads, one on each side of the county line.

Once construction is completed, Glen Dhu employees on the site will consist of security and maintenance workers.


http://www.thechronicleherald.ca/Business/1201432.html

Thursday, September 9, 2010

An ill wind on Lake Erie

The McGuinty government’s response to wind turbine opposition at Point Pelee reveals a green-energy policy in disarray

Adam Radwanski

From Tuesday's Globe and Mail


When Dalton McGuinty visited The Globe and Mail's editorial board earlier this year, one topic seemed to catch him off guard.

How, the Ontario Premier was asked, could his government be considering putting wind turbines off the shores of Point Pelee, in Lake Erie’s Pigeon Bay? As one of the most ecologically sensitive corners of the province, wasn’t it the sort of place that should be deemed off limits for energy development?

After broadly extolling the virtues of his Green Energy Act, Mr. McGuinty stumbled through an acknowledgment that he hadn't really given this specific issue much consideration. “You’ve raised something which I’ve not thought about,” he said. “I’m glad you're not in opposition.”

It was a strange thing for the Premier to say, even taking into account the number of files that cross his desk. The proposal for Point Pelee raised the ire of everyone from deep-pocketed residents to local mayorsto Margaret Atwood. Only a few weeks after his Globe visit, a pair of Mr. McGuinty’s own MPPs – Bruce Crozier and Pat Hoy – publicly came out against their own government's handling of the issue.

But Mr. McGuinty's answer to the editorial board epitomized one of the biggest flaws in his party's plans to attract wind energy development. Conceived in haste, with the aim of creating jobs and power as quickly as possible, the Liberal strategy was written too broadly to fully distinguish between good projects and bad ones.

In Point Pelee, a solution has come too late to avoid generating an avoidable degree of angst about green energy in general. And the solution itself is broad enough to have consequences elsewhere.

A RIPPLE EFFECT

Compared to other areas of the province, such as Prince Edward County, the Essex region is not a hotbed for the not-in-my-backyard sentiments that Mr. McGuinty has identified as a barrier to spreading wind turbines across the land.

A fruit basket at the southernmost tip of Canada – the town of Leamington is the country’s “tomato capital” – it seems to have been predisposed to welcome the hundreds of windmills that have popped up on local farms or are in development. While a few people on neighbouring properties aren’t happy, there has been little organized opposition to land turbines.

A drive through the region, however, quickly shows that the proposal to put as many as 150 turbines in the bay has struck a nerve.

“No wind turbines in our lake” signs dot the lawns of properties around Leamington and the neighbouring town of Kingsville – not just on the shoreline properties, but farther inland as well. In conversation, everyone seems to be aware of the issue.

Jim Krushelniski, who leads the protest group that distributes the signs, insists his opposition has nothing to do with NIMBYism. This is a slightly dubious claim, coming as it does while Mr. Krushelniski – a former Heinz executive – sits in the office of a luxury home that looks out on the lake. It’s hard to believe that the prospect of wind turbines spoiling his magnificent view hasn’t crossed his mind.

Nevertheless, he’s able to rhyme off a list of other concerns, including the potential impacts on drinking water and commercial fishing. The one that seems to have gotten the most traction is the effect on bird and bat migration – a major tourist attraction for Point Pelee, which sees more than 300 bird species pass through in the spring. (That’s also what’s attracted the attention of Ms. Atwood, a noted bird enthusiast with a home on Pelee Island, the popular destination about 18 kilometres from shore.) Given the tendency of turbines to make mincemeat of things airborne, it doesn’t require great imagination to figure out what would happen.

Fuelling the various worries is the fact that this is uncharted territory. Although there are several other proposals to build wind farms in the Great Lakes, on both sides of the border, none have actually been built. So it’s hard to know what exactly the environmental impact will be. And Essex, a place with a relatively dense population and a strong tourist industry, is a questionable place to test it out.

Indeed, very few people seem to think it’s a good idea to put wind turbines in Pigeon Bay. But there’s one notable exception: the people who want to build them.

SouthPoint Wind embodies the risks of unleashing a gold rush by offering premium prices for green energy, as Ontario has done. The company is run by a local housing developer and is viewed with considerable skepticism by more established developers – some of whom looked at Point Pelee and decided it wasn’t suitable for development.

SouthPoint is widely accused of doing a poor job of engaging locals in its planning. Mr. Crozier, the MPP for much of the area, draws an unfavourable comparison with Brookfield Renewable Power, the company that’s building many of the local land turbines. “We have one proponent who has worked with the community and gone the extra kilometre to communicate with the community,” he says. “My view is that SouthPoint has not made any extra effort whatsoever.”

Since 2006, when SouthPoint first brought forward its proposal, it appears to have been in a battle with residents. In 2007, when the province imposed a moratorium on offshore projects on the Great Lakes, the residents seemed to be winning. But the moratorium was lifted in 2008 leading up to the introduction of the Green Energy Act – legislation that simultaneously increased the financial incentives for wind development and reduced the barriers.

Aiming to expedite applications, the act greatly reduced the role of municipalities in the process. As a result, much of the case against SouthPoint’s proposal – which Essex’s communities had invested considerable resources in building – had to be tossed out the window.

By this past spring, residents felt like they were fighting an uphill battle to stop the project from going forward. And there became a growing mistrust of the Green Energy Act in general.

In early June, Mr. Crozier and Mr. Hoy (who represents the other part of the affected area) presented a petition against the project in the Ontario Legislature. They also signed their names to it – an unusual move for a pair of MPPs not known as renegades.

Only three weeks later, the government announced a change that suggested the issue had finally arrived on Mr. McGuinty’s radar. But rather than designating Point Pelee a no-go zone, it opted for something much less specific.

WIND AT THEIR BACKS?

On June 25, the government brought forward a proposed new rule for offshore wind development: Any turbines would have to be placed at least five kilometres from the shore.

For the record, officials deny that the rule is aimed at any one project. But within the industry, it’s widely believed it was a response to the Point Pelee dispute, and possibly to another controversial proposal for turbines in Lake Ontario off the shores of Scarborough.

Assuming the proposed rule becomes law this fall, most onlookers believe it will kill SouthPoint’s proposal. Leamington Mayor John Adams says he’s now 80 per cent sure the project won’t move forward; rival developers are even surer than that. (SouthPoint is declining interview requests until the province’s final decision.)

But the reality is that it’s not just the Point Pelee development that’s likely to get killed. The Scarborough plan, being advanced by Toronto Hydro, also faces grim prospects – as do most other proposals for the Great Lakes.

Requiring the turbines to be so far from shore makes them much more expensive – that is if they can be built at all, since they require relatively shallow water. Only one or two developers (notably Windstream Wolfe Island Shoals Inc., which plans to harvest offshore wind near Kingston) are said to be confident they can move forward.

Mr. Crozier, among others, would argue that discouraging that kind of development is a good thing, since the Great Lakes are too valuable a resource to trifle with. And while he thinks offshore wind still has “potential,” even Energy Minister Brad Duguid says he doesn’t think it’s “critical to our future energy needs.”

But that prompts the question: If offshore wind isn’t a priority, why did the government open the door to it in the first place?

The answer, it seems, is that it didn’t really give it much thought. Senior Liberals concede they didn’t anticipate the amount of interest, or the degree of controversy, it would generate.

So as on other fronts, such as the pricing of solar power, the government occasionally appears to be making up its green-energy strategy as it goes along.

If its one-size-fits-all policies caused problems, the Liberals now appear inclined to solve them with one-size-fits-all solutions.

“We said that if we really want to stand head and shoulders above others in North America in terms of being a welcoming economic environment, we would establish provincial standards,” Mr. McGuinty said during that editorial board meeting. “So you know what you get if you want to come here and invest.”

Those standards are evidently somewhat flexible. But before they change, they’re capable of creating a lot of bad will.

NSP had other biomass options

Pictou County, Sydney proposals deemed feasible

Two companies submitted alternative biomass power projects that would be "viable and offer good value" to Nova Scotia Power, according to an independent study released Wednesday.

Cape Breton Renewable Energy Inc. and Northern Pulp Nova Scotia Corp. submitted bids in April to the power company to sell electricity from burning wood waste, according to a review done by Deloitte & Touche at the request of Nova Scotia Power.

The Cape Breton firm proposed a 15-megawatt stand-alone biomass fuel facility, to be located at Harbourside Commercial Park, Sydney.

Northern Pulp submitted a plan to replace its existing biomass facility with a 48-megawatt co-generating plant at its mill in Abercrombie Point, Pictou County. The facility would use a combined biomass and liquid biofuel source. (Liquid biofuel is extracted from agricultural products like the rapeseed plant or soybeans.)

Until Wednesday, Nova Scotia Power wanted this information kept secret, but government regulators forced the utility to disclose some of the contents of the high-level review done on the alternative projects.

Nova Scotia Power is seeking regulatory approval to build its own 60-megawatt biomass plant, with a price tag of $208 million. NewPage Port Hawkesbury Corp. would operate the plant, using an old burner at the plant, valued at $80 million.

Hearings into that proposal resume today in Halifax before regulators.

A hearing into that proposal got underway in July, but was halted by review board chairman Peter Gurnham in order to compare the $208-million biomass project with the other renewable energy proposals the utility had solicited.

Deloitte & Touche does recommend one of the projects over the other, but that was blacked out in the 48-page document.

Most of the report has been blacked out, including the detailed analysis done on each project.

Nova Scotia Power says it needs the proposed $208-million biomass project to meet the province’s 2013 renewable energy standards. The utility is targeting an in-service date of 2012 and must get approval from the review board, which rejected a similar bid last summer.

In July 2009, the board said it lacked the authority to approve in advance Nova Scotia Power’s plan to buy electricity from NewPage under the previous proposal.

This time, the utility is submitting the project as a capital expense, not a power purchase agreement. The utility requires regulatory approval for any expenses exceeding $25,000.


http://www.thechronicleherald.ca/Business/1200738.html

Wednesday, September 8, 2010

Partial disclosure

Review board orders NSP to produce more information about biomass project

A key document discussing how Nova Scotia Power’s proposed $208-million biomass power project stacks up against other renewable energy projects must be made public, government regulators ruled Tuesday.

The Nova Scotia Utility and Review Board said it does not agree that the whole document, prepared by Deloitte & Touche for the power company, should be kept secret.

Instead, the regulator has ordered Nova Scotia Power’s lawyer Dan Campbell to submit a "redacted version" of the document with its findings and mandate.

The utility says it will file a revised version today with the board, a day before a hearing reconvenes into Nova Scotia Power’s controversial proposal to generate electricity using wood waste in Point Tupper.

Nova Scotia Power labelled the Deloitte & Touche report confidential when it was filed to government regulators last week.

While the board understands there is competitive information surrounding the bids of the other renewable energy projects, the regulator believes other aspects of the report can be made public.

On Thursday, a hearing resumes into Nova Scotia Power’s request to spend $208 million to build and own a biomass plant that NewPage Port Hawkesbury Corp. will operate, using an old burner at the plant valued at $80 million.

A hearing into the biomass project got underway in late July but was abruptly halted by the regulator’s board chairman in order to compare the biomass project with the other renewable energy proposals the power company had solicited.

The Deloitte & Touche report was filed Sept. 2 and it is not the only piece of evidence in this hearing that has been classified confidential.

Twenty-two other pieces of evidence, out of a file of 61 exhibits, have been kept under wraps, mostly at the request of Nova Scotia Power.

In April, Nova Scotia Power applied for approval of a capital work order to build the biomass power plant. The same month it issued a request for proposals for other renewable energy projects.

This latest order comes four months after the board told Nova Scotia Power it was upset with the number of documents filed by the power utility that were being marked confidential without proper substantiation.

In its decision on the use of confidential documents, "board decisions must contain sufficient information so that a reader can clearly understand how the board reached its decision," the board wrote.

It also said the public and the media should have maximum access to evidence filed by the power company when it comes before the board for approval of power rates and capital expenditures.

John Merrick, Nova Scotia’s consumer advocate, told The Chronicle Herald last week he would be reviewing the documents labelled "confidential" filed with the biomass project to see if it is justified.

"Any time there’s a large volume of redactions or a large volume of evidence that has been kept confidential, you should be suspicious and you should be concerned that it is being misused or overused," said Merrick

http://www.thechronicleherald.ca/Business/1200652.html

Saturday, September 4, 2010

N.B. municipalities warned about unrealistic profits from wind projects

The Canadian Press
Published in the Amherst Daily News
1st September 2010


FREDERICTON - New Brunswick municipalities are being warned that a government document on community wind farms could mislead them into spending millions of dollars in projects that could end up losing money.

The Energy Department recently published a paper called New Brunswick Community Wind Projects - getting to the Tipping Point.

The paper includes a mock business plan based on NB Power paying 10 cents a kilowatt/hour plus an inflation factor for wind generated electricity.

The province wants to eventually buy 75 megawatts from community-owned renewable energy projects, but the business plan assumes a small wind farm would operate 34.8 per cent of the time.

Raphael Shay, a spokesman for the Alliance for Community Energy, said Monday that 30 per cent is more realistic and that would have a drastic effect on a project's cash flow.

he said that only the largest wind farms in Canada have a capacity of 34.8 per cent.

"The Department of Energy is trying to justify the unrealistic price they set for electricity from community wind projects by assuming far more electricity production than industry averages," he said.

A Summerside P.E.I. wind farm was expected to have a capacity of 36 per cent before it was built and now operates at well below 30 per cent, he said. that $27 million PEI project had a $21 million government grant, he said.

The New Brunswick mock business plan is based on a community raising 39 per cent of the cost of a wind project and borrowing 70 per cent, although one alternate plan includes a $5 million government grant.

The mock business plan suggests that a 15 megawatt wind farm with 10 turbines, each 80 metres high with 82 metre diameter blades, would cost between $30 million and $35 million to build and would have a positive cash flow of just more than $1 million a year on annual revenues of $4.6 million.

Shay said that if that wind farm had a capacity of 30 per cent rather than 34.8 per cent, then it would produce 14 per cent less power and revenue.

He said the Danish Wind Industry Association, which estimates that 12 per cent of the world's energy will come from wind power by 2020, suggests that 25 to 30 per cent is a more realistic capacity for a small wind farm.

He said small wind farms have less capacity than large wind farms.

If a facility has 10 turbines and one goes down for maintenance, then it loses 10 per cent of its capacity.

By comparison if a wind farm has 100 turbines and one stops working, it only loses one per cent of its capacity, he said.

This variables really impact the overall project," Shay said.

Biomass rationale a secret

NSP won’t release renewable energy analysis that led to project

Nova Scotia Power continues to use its confidential stamp, despite a government regulator’s order to the power company for more transparency to the public and the media.

On Thursday, a controversial hearing reconvenes into Nova Scotia Power’s request to spend $208 million to build a power plant using waste wood in Port Hawkesbury. The utility plans to own the biomass plant and NewPage Port Hawkesbury Corp. will operate it, using an old burner at the plant valued at $80 million.

But the public will not see how the biomass project stacks up against other renewable energy projects the power company solicited.

A key document providing an analysis of these renewable energy projects has been classified confidential. Twenty-two other pieces of evidence, out of a file of 61 exhibits, have been kept under wraps, mostly at the request of Nova Scotia Power.

"Any time there’s a large volume of redactions or a large volume of evidence that has been kept confidential you should be suspicious and you should be concerned that it is being misused or overused," said consumer advocate John Merrick.

Merrick says he is going to review all the documents labelled "confidential" to see if it is justified.

"There’s a practical aspect to this; obviously every single document that NSPI wants to keep confidential . . ., they shouldn’t have to go down to the board and have a hearing to decide. So they’re given a certain amount of discretion . . . to claim confidentiality . . . but it is always subject to review or challenge and will depend on what they try to keep confidential," said Merrick Friday. He represents the utility’s 440,000 customers.

In April, Nova Scotia Power applied for approval of a capital work order to build the biomass power plant.

The same month it issued a request for proposals for other renewable energy projects.

A hearing into the biomass project got underway in late July but was abruptly halted by the board chairman in order to compare the biomass project with the other renewable energy proposals the power company solicited.

When the hearing resumes Thursday it will deal with this project review and likely be held behind closed doors since the document has been stamped confidential, said Merrick.

Review board spokesman Paul Allen said the board tries to get as much information into the public domain as possible.

Allen said in this matter there is competitive information and business agreements that are being discussed and in the process of being developed that are sensitive.

In May, the board told Nova Scotia Power it was upset with the number of documents filed by the power utility that were being marked confidential without proper substantiation.

In its decision on the use of confidential documents, "board decisions must contain sufficient information so that a reader can clearly understand how the board reached its decision," the board wrote.

It also said the public and the media should have maximum access to evidence filed by the power company when it comes before the board for approval of power rates and capital expenditures.


http://www.thechronicleherald.ca/Business/1200200.html

Friday, September 3, 2010

Let’s hope council doesn’t waffle on wind power

http://www.thechronicleherald.ca/Opinion/1199640.html


It will hardly come as a shock that Halifax regional council has been kicking around the issue of wind power for two years and has yet to make any policy decisions.

What will be more of a shock is if the crew at city hall actually manage to muster the political backbone to adopt a draft bylaw on wind power that has been recommended by staff.

It could save significant time while helping to get Nova Scotians — more than 40 per cent of whom live in the Halifax region — on the road to consuming more green power.

There is no question that wind power is not universally popular. The debate rages on about whether wind turbines are an eyesore, a health risk or a sign of a modern community that is trying to get beyond chronic dependence on tradition power sources to produce electricity.

In this province, burning cheap, dirty coal springs to mind.

No one likes paying higher power bills and the rates consumers face for domestic electricity remain among the highest in Canada.

But while the NDP government has had to back down on the aggressive timelines of its green power commitments in its energy strategy, it is still on the right road in terms of encouraging green energy. Wind turbines are an obvious part of such a strategy.

But the province has left a large chunk of the dirty work — determining setbacks and other restrictions on wind farms — to the province’s municipalities. That will leave an obvious mishmash of regulations that could see some municipal governments fighting over future proposals due to the lucrative tax revenue they will bring.

Meanwhile, residents who want to weigh in on the side of eyesore-health risk argument will be doing all they can to send the wind farms packing to the next municipality down the road.

In Halifax, municipal staff are recommending that council approve a bylaw that will allow turbines as a right in pre-approved areas and based on specific setbacks rather than having each potential project jump through the hoops that inevitably come from development agreement applications.

The neighbour-against-neighbour debates have been common in the wind power issue not only in North America, but around the globe. While some people welcome the turbines, along with the clean power, jobs and tax dollars they bring, others fear noise pollution, flickering lights and illnesses they say turbines can cause.

Paul Dunphy, the municipality’s director of community development, told councillors last month that while turbines will always draw criticism from some quarters, they are an integral part of a clean energy future.

"Turbines will always be tall, they will always be on high points of land and they will always be obvious. And there will always be people who object to them."

Officials from Nova Scotia municipalities already hosting turbines would say amen to that.

But there was limited opposition around the Halifax council table, with councillors voting to have the bylaw drafted and then sent for additional committee work and a public hearing.

"We need to move forward and show some support for this," Coun. Darren Fisher (East Dartmouth-The Lakes) said during the debate.

"All energy sources have drawbacks and probably every energy source has more drawbacks than wind energy."

Imagine trying to build, in today’s climate, the sort of massive coal-burning power plants that are now serving the province’s energy needs. In comparison, wind farms seem pretty neutral.

A draft bylaw is one thing; voting to make it law will be another matter. Hopefully council can manage to make a decision and then move forward within months rather than the two years it has already taken to get this initiative moving.

Cleaner power is worth the effort.

~~~~~~~~~~

COMMENTS

Welcome back, Marilla

"Turbines will always be tall, they will always be on high points of land and they will always be obvious. And there will always be people who object to them."

Denmark, arguably the world's largest consumer of wind generated electricity (Wind power provided 18.9% of electricity production and 24.1% of generation capacity in Denmark in 2008, Denmark was a pioneer in developing commercial wind power during the 1970s, and today almost half of the wind turbines around the world are produced by Danish manufacturers such as Vestas - Wikipedia)

Optimal water depth is between approximately 15 - 50 feet of water. I wonder, has any thought been given to locating these windmills in the water?


Do Your Homework Marilla

View the videos and read of personal experiences on "National Wind Watch" and "Wind Concerns Ontario".

Learn how Ontario municipal councils have lost any say on industrial wind turbine site selections, and how real estate values drop 40-60%.

Watch the videos of folks who were forced to leave their homes due to wind turbine low frequency noise (LFN), and remember that LFN is used as a military weapon - against enemies...

Remember how the Halifax wind company honcho, Ministers of Environment, local councillors, et al, turned their backs on the D'Entremont family of Pubnico Point, and how our media ignored their call for help.

You failed the industrial wind turbine test Marilla, but so has McGuinty. Watch as he's blown out of power.


let's get our priorities straight

To hear people agonizing over "eyesores" is really sad. That is such a subjective issue. We've got cellphone towers and billboards all over the place. Health issues are certainly worth worrying about. Wind turbines produce noise, and agencies all over the world - esp WHO - have produced clear guidelines as to how much noise is too much, with "too much" being that which affects your health. As long as the turbines are parked in places where the noise levels fall below these limits, no one should need to complain. Typically, standards usually specify 35 dBa at night and 55 dBa in the daytime as levels which, when exceeded, hurt people. As far as eyesores go, get over it. Beats having another coal belcher and we probably can't afford nuclear.


Denmark Fails to Reduce Emissions

Wikipedia is not a reliable source for information on Climate Change, AGW, IPCC Report-Errors, nor Industrial Wind Turbines.

One of their honchos has been removed/fired for removing Climate Change information.

Denmark's emissions haven't been reduced after spending taxpayers' billion$ on wind energy, while their power rates increased by 30%. They can't afford to upgrade their power grids, and have wasted years on this most inefficient, expensive, and unreliable source of non-dispatchable energy.

It will be decades before wind energy storage solutions are discovered, so in effect the wind turbine cart has been put before its horse - go figure.


Wind Won't Replace Coal/Gas Fired Power Plants

Many believe industrial wind turbine projects will replace NS Power plants, not realizing these plants will be required to run 24/7 as back-up during low wind or calm periods.

Wind energy is not dispatchable. There will be no reduction in NS Power plant emissions - period.


What's the Problem

Everyone whats cheaper power bills but they don't want anything to change. You can't have your cake and eat it too. Turbunes and solar power are here, get used to it. They are trying a tidal generation in the Bay of Fundy also. I wish we could get tax breaks to have something installed for home use. The by-laws and costs right now are far too restrictive. Also in most other provinces if you generate more power than you use the supplier must buy it back from you. IE you can make money off it. Where as here in NS, NS Power is not obligated to buy back and they can cap how much they buy back. Imagine where NSP would be if we all had the capabilty of producing our own power? OOP's I forgot where I was for a minute. Forgive me.


I wonder why the NIMBY crowd

I wonder why the NIMBY crowd are acting as if Wind Turbines have never been erected anywhere else in the world, and that research has never been conducted? This is a well-established technology. Any historical data from past studies, and the resulting legislation in other countries should be no less applicable to Nova Scotia. Yet it remains untapped as a resource for wind turbine placement guidelines and examples of good legislation? I don't get it. CountryHick mentioned WHO as a source of actual guidelines based on science?

Common Sense - Where are these 40-60% drops in property value occurring? Everything I read says that property values are at all-time highs, are highly over-inflated, and the bubble is yet again about to burst. Perhaps your claimed drops are attributable to real estate simply being massively over-priced. And, did the media turn their backs on the family in Pubnico, NS? It seems to me that the media gave them as much coverage as they wanted. What about Every other homeowner in proximity to that particular wind project? Only 1 family seemed to have issues? Have property values plummeted in NS communities near wind projects?


stop piddling around

start building the Nuclear Plant now!




Follow the Money
This comment has been edited.

Mr. Blades, I believe I read a comment from you on another site, where you stated the SW Shore was a perfect location for industrial wind turbines. Do you realize we are trying to reinvent a decade old farce that will not remove our dependence on coal/gas fired plants? Go to the videos on "National Wind Watch" which cover wind energy operations in Australia, Denmark, Scotland, Ireland, Britain, U.S.A., and Canada. Take note that today's news shows Denmark's national power company has been forced offshore for all future wind turbine projects. How would your fishing communities deal with that threat? See from the videos how real estate values drop like a bald eagle hit by a turbine blade, and note that the majority of the homeowners are not wealthy people who can afford to take such a loss on the largest investment in their life. In the few cases where the wind companies have been forced to buy the affected homes, it has been at 60% or below the appraised real estate value. No sir, it appears the true wind lovers are those who have monetary gain in mind, not the environmental well being of rural communities. When your neighbours educate themselves and their friends on the truth behind the wind turbine industry and then follow the money, I doubt if they'll hop on your bandwagon Mr. Blades, and will be the first to question their municipal councils on all industrial wind turbine decisions made without their approval.


Stick With What Works

The 2 huge problem for wind power is the cost first, and then the variability, second. In Ontario the power companies are forced to pay between 13.5 cents and 19 cents/KWH to buy wind power from the suppliers, average this at 15 cents, add in all the other costs and you have about 20.5 cents to the consumer, we now pay about 12 cents, so this is about a 66% increase in power rates, guaranteed to drive businesses and jobs out of the province. And then there is the variability, you get power provided, the wind is blowing, provided it blows at a speed that will generate peak power, not too strong, not too slack, provided the blades don't ice up in winter, or are not knocked off line by lightning, or wrecked by a hurricane, or not down for expensive refurbishing, every 12 years or so, not all that reliable, so you end up needing an alternate, reliable back-up plan, you pay twice for facilities, not the greatest deal I wouldn't think. Dirty coal, well look out your window, you will see clear blue sky, fresh clean air, we have pure water and fertile soil, so why drive up our rates with expensive sources when we already know how to generate clean power.

Wednesday, September 1, 2010

Gulf Shore committee blindsided by comments

Darrell Cole
Amherst Daily News
Published August 29th, 2010

Chair disappointed with comments from wind farm proponent


PUGWASH - The chair of the Gulf Shore Preservation Association is disappointed with comments made by the head of a company attempting for a second time to build a wind farm near Pugwash.

Lisa Betts was surprised to read comments from Charles Demond in this newspaper and another media outlet in which the president of Atlantic Wind Power accuses a vocal minority of trying to kill his project.

"We're not a minority at all. The feelings we have are those of the entire community," Betts said Friday. "We have some serious problems with this project that go way beyond its actual footprint."

Demond attended the association's annual general meeting in Pugwash a week ago to talk about his company's scaled down plans to construct a wind farm that would include 11 or 12 turbines as opposed to the 20-27 turbines proposed several years ago.

While there would be fewer turbines, the association is concerned that their height and that of their blades could exceed 500 feet.

Betts believes Demond will find more people are opposed than gray-haired residents and she also stressed her group has a lot of respect for those property owners who may host the turbines.

http://www.amherstdaily.com/News/Local/2010-08-29/article-1707593/Gulf-Shore-committee-blindsided-by-comments/1